Timeline/Milestones for Work:
Task/Subtask Number and Name
Milestones/Deliverables
Due Date or Completion
Date
1.0 Pre-Execution Activities
Completion of internal and
Completion due by six (6)
external pre-execution activities I months after Task Order
Award
2.1 Study Protocol (Draft)
Delivery of draft Study Protocol
for in vitro study
Completion due by one (1)
month after Task Order
Award
2.2 Study Protocol (Final)
Delivery of final Study Protocol
Completion due by two (2)
Ebola virus
for in vitro study
months after Task Order
Award
2.3 Characterization of inhalation
Completion on inhalation system I Completion due by six (6)
system with Ebola virus
performance with both small and I months after Task Order
large particle aerosols containing I Award
2.4 Go/No-Go
Meet with BTCP and NIAID
sponsors review deliverables
form subtask 2 and make Go/NoGo determination
Completion due by six (6)
months after Task Order
Award
3.1 Study Protocol (Draft)
Delivery of Draft Study Protocol
for Small Particle Aerosol in vivo
study
Completion due by four (4)
months after Task Order
Award
3.2 Study Protocol (Final)
Delivery of Final Study Protocol
for Small Particle Aerosol in vivo
study
Completion due by four (5)
months after Task Order
Award
3.3 Estimation of median lethal
dose of small particle aerosols
Completion of the estimation of
the medial lethal dose of small
particle aerosols containing Ebola
virus in nonhuman primates
Completion due by eighteen
(18) months after Task
Order Award
3.4 Go/No-Go
Meet with BTCP and NIAID
sponsors review deliverables
form subtask 3 and make Go/NoGo determination
Completion due by eighteen
(18) months after Task
Order Award
4.1 Study Protocol (Draft)
Delivery of Draft Study Protocol
for Large Particle Aerosol in vivo
study
Completion due by eleven
(11) months after Task
Order Award
4.2 Study Protocol (Final)
Delivery of Final Study Protocol
for Large Particle Aerosol in vivo
study
Completion due by twelve
(12) months after Task
Order Award
4,3 Estimation of median lethal
dose of large particle aerosols
Completion of the estimation of
the medial lethal dose of large
particle aerosols containing Ebola
virus in nonhuman primates
Completion due by twentysix (26) months after Task
Order Award
pg. 3